A Schedule Prediction Accuracy Chartāalso known as a milestone slip chartāis a powerful visual tool for tracking how project milestone forecasts evolve over time. It helps teams identify schedule risks early and assess the reliability of their delivery predictions.
This chart, as illustrated below, is an X-Y scatter plot where:
Each point on the chart reflects the forecasted delivery date of a milestone at a particular time. By connecting these points over successive reporting periods, you can observe trends in schedule predictions.
By analyzing these trends, project managers can assess the stability of their schedules and identify areas requiring attention.
Understanding the patterns in a milestone slip chart can provide insights into the projectās health: